Jeremy Ranch Sewer Improvement Project

In the coming weeks, the Snyderville Basin Water Reclamation District (SBWRD) will be replacing several sewer lines within the Jeremy Ranch golf course. These sewer lines were installed in the early 80’s and need to be replaced. SBWRD is working with the Jeremy Ranch Golf Course to complete this work prior to the general golf course work that is scheduled for this spring and summer.

Sewer line work will be in two phases:

Phase 1
Location: In the Hole #2 area (between Rasmussen Road, Silver Spur Road, and Saddleback Road). Construction access will be from Rasmussen Road.
Details: Remove and replace approximately 750 feet of 8” sewer lines.
When: Work for this phase will begin February 26 and will take between 2 and 4 weeks to complete.
Neighborhood Impact: Bypass pumping will be required, so there will be some equipment located within the road between 8710 and 8720 Silver Spur Road and between 3675 and 3689 Saddleback Road.

Phase 2
Location: In the Hole #5 area (behind the homes on Lariat Road, from 3750 to 3970 Lariat Road). Construction access will be from Jeremy Ranch Road between 9175 and 9225 Jeremy Ranch Road.
Details: Remove and replace approximately 1,650 feet of 8” sewer lines, reconnect sewer laterals, and construct a golf cart path that can support SBWRD maintenance vehicles.
When: It is anticipated that work for this phase will follow the Phase 1 work. Start date will be dependent on our contractor’s schedule and on the snowpack in the area. Construction will be completed by July 3 at the latest.
Neighborhood Impact: SBWRD and our contractor will work with each homeowner along Lariat Road to coordinate all sewer line reconnections.

SBWRD contacts for the project are:

Trent Bay (Project Engineer): 435-731-0809, tbay@sbwrd-ut.gov
Kevin Berkley (District Engineer): 435-731-0424, kberkley@sbwrd-ut.gov